Progress Section 1 Semarang - Demak Toll Road Project Reaches 24.66%
Monday, 11 November 2024

The Semarang-Demak Toll Road Section 1 Kaligawe-Sayung which spans the total of 10.64 kilometers is planned to be functional in early 2027. This lane will connect Section 2 Sayung-Demak which spans the total of 16.31 kilometers on land and has been operational since 25 February 2023. The construction of Section 1 Kaligawe-Sayung which stretches upon the sea and to be completed by the government is currently in the land reclamation process with the progress reaching 88.15% and the physical construction progress reaching 24.66%.