Pembangunan MRT Jakarta Fase 2A Capai 58%

Wednesday, 28 January 2026

The construction progress of Phase 2A MRT Jakarta route Bundaran HI-Jakarta Kota has reached 58.89% as of December 2025, exceeding the target of 53.29%. The construction of Phase 2A comprises three work package with the progress of CP201 package spanning from Bundaran HI to Monas has reached more than 91.16% and is estimated to be completed and operational in 2027. Meanwhile, CP202 package of Harmoni-Mangga Besar route has progressed by 61.59% and CP203 has progressed by 80.93%.