PT MRT Jakarta (Perseroda) recorded the construction progress of Phase 2A MRT Jakarta route Bundaran HI-Kota has reached 61.80% as of 25th June 2026. MRT Jakarta aimed to first complete the Bundaran HI-Monas Segment 1 by the end of 2027, followed by Harmoni-Kota Segment 2 by the end of 2029. Based on MRT Jakarta’s data, the progress for CP201 work package of Bundaran HI-Harmoni has reached 93.50%, followed by CP203 Mangga Besar-Kota at 86.03%, and CP202 Harmoni-Mangga Besar at 67.04%.