PT MRT Jakarta has completed all Phase 2A north-south tunnels after tunnel boring machine (TBM) 2 broke through the south wall of Mangga Besar Station on 4 November 2026. The southbound tunnel was built in two stages, Harmoni-Sawah Besar (July-October 2025) and Sawah Besar-Mangga Besar (February-July 2026), while the northbound tunnel toward Kota Station was finished in July 2026, with six TBMs used in total. Segment 1 (Bundaran HI-Monas) is targeted to operate by end-2027, while Segment 2 to Kota Station is targeted for end-2029.